Temporary Works (Scaffolding)
Structural design and inspection of a temporary scaffolding system over a fast-flowing stream to support SH1 bridge upgrade works.
Upgrading critical infrastructure often requires working in challenging and high-risk environments. For this SH1 bridge over a fast-flowing stream in the central North Island, safe access beneath the structure was essential to enable upgrades to be carried out.
Cook Costello was engaged to design and inspect a complex temporary scaffolding system constructed above a confined waterway and steep rock banks. Although temporary in nature, the structure was required to safely resist construction loads, wind actions and seismic demands that may occur throughout the duration of the works.
Our structural team:
Undertook detailed structural analysis of the scaffold system
Designed bracing, support arrangements and load paths to ensure global stability
Produced design documentation for construction and site coordination
Carried out inspections during erection to confirm compliance with the design intent
The result was a stable, compliant temporary works solution that enabled the contractor to proceed efficiently and safely, with no delays attributable to the access structure.
We regularly deliver temporary works design for bridge upgrades, earthworks and ground improvement works, retaining systems, access platforms and complex construction staging. Every site presents unique constraints, and we work closely with contractors to develop practical, buildable solutions that manage risk while maintaining programme and cost certainty.